UCL E-Science Artemis Work

atlas-ucl-offline

Last Update: 16/06/04 (PS)

Key:
    Not started
    Awaiting input from some other activity
    Completed and tested

Published Deliverables (from PMB 2/5/04)

Date Item Status
09/2004 First Report Pending
09/2005 Complete Package development Pending
09/2006 Performance Studies - Use in Phyisics TDR - User feedback Pending
03/2007 Final version of analysis ready for data taking; full user guide Pending
09/2007 Evaluation with real data (document) Pending
12/2007 Revised Artemis release (package) Pending
03/2008 Final evaluation document Pending


Fine Deliverables

Date Due Item In Charge Participants Status Status Date Comment
28/05/04 ArtemisAlgs Jobs cleaned up and into RTT PS- Underway 24/05/04 Artemis HiggsMass in RTT. No results from RTT seen yet.
04/04/04 jobOptions.txt->python PS- Underway 04/08/04 -
08/08/04 Solve apparant initialisation problem for PartPropSvc PS, C.C-T- Underway 04/06/04 problem only occurs in Atlfast, but only when running Artemis
04/06/04 Make BPhysExample work under 8.2.0 PS- Underway 08/06/04 Sufferes run time error - library not built as component library


Unscheduled ToDo

DateByItem
24/05/04PS Ensure Doxygen gets enough comments (inline doc)
24/05/04PS Create Artemis test jobs that input from POOL
24/05/04PS Extend toolbox - labelled associations
24/05/04PS Extend toolbox - pursue BPhys objects with data/cutters


Comments

Date By Item
6/5/04 PS xxx