Prototype-ROB-IN Work Breakdown Structures ========================================== (20-May-1996, R.Cranfield, UCL) ------------------------------------------------------------------------------- P-ROB-IN WBS ------------------------------------------------------------------------------- B.1 Produce ROB-IN specification B.1.1 Produce URD Description: Describe functionality of ROB-IN in terms of user requirements. Deliverables: ROB-IN URD. Schedule: Week 2, May-1996 Status: Completed B.1.2 Produce outline design Description: Describe overall functionality and interfacing philosophy. Deliverables: Outline design. Generic block diagram. Schedule: Week 2, Jun-1996 Status: Started B.1.3 Produce detailed functional spec Description: Describe in detail the functional components, interfacing and operation of the prototype ROB-IN. Deliverables: Detailed functional spec. Schedule: Week 2, Oct-1996 Status: Not started B.1.4 Choose buffer manager processor Description: Investigate options for the buffer manager processor in light of the evolving ROB-IN specification. It is not intended to perform in-house hardware studies; sources of information will be processor specs, performance reports, and any existing in-house experience. Deliverables: Report justifying processor choice. Schedule: Week 4, Dec-1996 Status: Not started B.2 Produce ROB-IN prototype hardware B.2.1 Produce design Description: Deliverables: Circuit diagrams. PAL code. Schedule: Week 4, Mar-1997 Status: Not started B.2.2 Produce layout Description: Deliverables: ROB-IN prototype board layout description files. Schedule: Week 4, Apr-1997 Status: Not started B.2.3 Manufacture board Description: Deliverables: Unpopulated ROB-IN prototype board Schedule: Week 4, May-1997 Status: Not started B.2.4 Populate board Description: Deliverables: Populated ROB-IN prototype board Schedule: Week 1, Jun-1997 Status: Not started B.2.5 Produce documentation Description: Deliverables: ROB-IN prototype board programmers guide. Schedule: Week 4, May-1997 Status: Not started B.3 Produce ROB-IN prototype test software B.3.1 Produce test software Description: Deliverables: ROB-IN test programs. Schedule: As required during testing (ends Week 4, Dec-1997) Status: Not started B.4 Test ROB-IN prototype hardware B.4.1 Test/debug board Description: Deliverables: Working ROB-IN prototype board. Schedule: Week 4, Dec-1997 Status: Not started B.5 Produce ROB-IN software B.5.1 Design software Description: Design ROB-IN buffer manager software. Deliverables: Software design description. Schedule: Week 4, May-1997 Status: Not started B.5.2 Produce code Description: Produce ROB-IN buffer manager code. Deliverables: ROB-IN buffer manager code Schedule: Week 4, Sep-1997 Status: Not started B.5.3 Test/debug code Description: Test/debug ROB-IN buffer manager code. Deliverables: Working ROB-IN buffer manager code. Schedule: Week 4, Dec-1997 Status: Not started B.6 Produce ROB-IN documentation B.6.1 Produce ROB-IN documentation Description: Document ROB-IN use and operation. Deliverables: ROB-IN user manual. Schedule: Week 4, Dec-1997 Status: Not started ------------------------------------------------------------------------------- -------------------------------------------------------------------------------