== To Do == | == To Do == | ||
'''Immediate work: Reply Project Name to Module Lead''' | |||
*check with professor or report what name was given (low importance vs actual work) | |||
*(also begin literature reading) | |||
'''Deadline: 10th November 1400h''' | '''Deadline: 10th November 1400h''' | ||
requirements: | requirements: | ||
Line 18: | Line 22: | ||
re-structure for final report. | re-structure for final report. | ||
'''feedback meeting with supervisor required within 3 weeks of submission.''' | '''feedback meeting with supervisor required within 3 weeks of submission.''' | ||
'''Deadline: 29th Nov Group Meeting Presentation''' | |||
requirements: | |||
*create presentation with suitable context to work, and updates on progress | |||
'''Deadline: 29th Nov Group Meeting code''' | |||
requirements: | |||
*task 1: write code that writes a json, to familiarise | |||
*task 2: develop script that opens list of certain format and cycles the list and then opens again | |||
*task 3: connect and adapt script to using D3 to display the code. Try to not use Flask and modularise the code scripts. | |||
== Completed == | == Completed == |
Latest revision as of 10:40, 17 October 2025
Electronic log for Danial Saeed
To Do
Immediate work: Reply Project Name to Module Lead
- check with professor or report what name was given (low importance vs actual work)
- (also begin literature reading)
Deadline: 10th November 1400h requirements:
- you 1500 words max.
- must include 3 sections:
- short literature survey
- project aims/objectives
- conclusions.
- literature survey: brief, referenced overview showing understanding of topic (no detailed theory).
- aims/objectives: expand on title; outline what will be done and how, linked to Gantt chart.
- Gantt chart must be created:
- first list project tasks
- compile the chart to include in the planning document.
- confirm with supervisor/research group members
- conclusion: short summary of progress + plan for supervisor meetings; reflect this in Gantt.
re-structure for final report. feedback meeting with supervisor required within 3 weeks of submission.
Deadline: 29th Nov Group Meeting Presentation requirements:
- create presentation with suitable context to work, and updates on progress
Deadline: 29th Nov Group Meeting code requirements:
- task 1: write code that writes a json, to familiarise
- task 2: develop script that opens list of certain format and cycles the list and then opens again
- task 3: connect and adapt script to using D3 to display the code. Try to not use Flask and modularise the code scripts.